Scott Road Shed Project

Landscaping

CURRENTLY UNDER CONSTRUCTION - Earthworks & Site Preparation in Progress

Our Scott Road shed project is well underway, and the team has been making steady progress transforming this site.

The project began with extensive site preparation, including opening up 450m² of driveway and shed pad to establish a solid footprint for the build. From there, we tackled the first major phase of earthworks, removing over 200m³ of clay to ensure the ground conditions were suitable for a stable foundation.

With the shaping and excavation complete, we’re now preparing to bring in 120 tonnes of hardfill. This stage will reinforce the driveway and shed base, creating a durable, long-lasting surface that can handle heavy use and provide reliable access to the site.

Throughout the process, our focus remains on accuracy, efficiency, and delivering high-quality results. Every step is planned and executed to support the next phase of construction while keeping the project running smoothly from start to finish.

From sheds and driveways to large-scale earthworks and full site development, our team has the expertise, equipment, and experience to manage projects of any size. Follow along as this Scott Road project continues to take shape, with more updates coming soon!